AbstractThis article studies cost‐plus‐time (A+B) procurement contracting with time incentives in the highway construction industry. In the presence of construction uncertainty, the contractor's actual completion time may deviate from the bid completion time, and the A+B contract design is not ex post efficient. Using data from highway procurement contracts in California, we show that an ex post efficient lane rental contract would reduce the social cost by $41.39 million (43.11%) on average. Moreover, the average commuter cost would decrease by $62.06 million (78.96%), suggesting a substantial reduction in the construction externality to commuters from lane rental contracts.
Contract theory (moral hazard, adverse selection)
Contract theory (moral hazard, adverse selection)
| selected citations These citations are derived from selected sources. This is an alternative to the "Influence" indicator, which also reflects the overall/total impact of an article in the research community at large, based on the underlying citation network (diachronically). | 1 | |
| popularity This indicator reflects the "current" impact/attention (the "hype") of an article in the research community at large, based on the underlying citation network. | Average | |
| influence This indicator reflects the overall/total impact of an article in the research community at large, based on the underlying citation network (diachronically). | Average | |
| impulse This indicator reflects the initial momentum of an article directly after its publication, based on the underlying citation network. | Average |