doi: 10.1007/11564751_19
This paper reconsiders the most basic scheduling problem, that of minimizing the makespan of a partially ordered set of activities, in the context of incomplete knowledge. While this problem is very easy in the deterministic case, its counterpart when durations are interval-valued is much trickier, as standard results and algorithms no longer apply. After positioning this paper in the scope of temporal networks under uncertainty, we provide a complete solution to the problem of finding the latest starting times and floats of activities, and of locating surely critical ones, as they are often isolated. The minimal float problem is NP-hard while the maximal float problem is polynomial. New complexity results and efficient algorithms are provided for the interval-valued makespan minimization problem.
| selected citations These citations are derived from selected sources. This is an alternative to the "Influence" indicator, which also reflects the overall/total impact of an article in the research community at large, based on the underlying citation network (diachronically). | 14 | |
| popularity This indicator reflects the "current" impact/attention (the "hype") of an article in the research community at large, based on the underlying citation network. | Average | |
| influence This indicator reflects the overall/total impact of an article in the research community at large, based on the underlying citation network (diachronically). | Top 10% | |
| impulse This indicator reflects the initial momentum of an article directly after its publication, based on the underlying citation network. | Top 10% |