Adaption of structured analysis design techniques methodology for construction project planning

Agyekum-Mensah, G; Knight, A; Pasquire, C;
Open Access English
  • Published: 01 Jan 2012
  • Publisher: ARCOM, Association of Researchers in Construction Management
  • Country: Italy
Abstract
The construction industry has been heavily criticised by researchers and governmental organisations for its performance especially excessive delay. Ballard and Howell (2003) indicated that only about 50% of the tasks on weekly work plans are completed by the end of the plan week. This is a result of a lack of either effective project planning or effective production control. It therefore seems the traditional approach of planning is insufficient to meet the current demand and complexity of construction projects. This paper proposes to critically evaluate the adaptation of Structured Analysis Design Techniques (SADT) methodology as a tool for project planning. SA...
Related Organizations
38 references, page 1 of 3

Agyekum-Mensah G. (2012) Defining Contribution of Effective Project Management: 4Es The necessary tool, "Proceeding of fourth annual RPC Conference", pp 53-59, Nottingham, U K ,

Aibinu A . A . and Jagboro G. O (2002) The effects of construction delays on project delivery in Nigerian construction industry, "Int. Journal of Project Management" 20, 593-599 [OpenAIRE]

Al-Momani A., H . (2000), Construction delay: a quantitative analysis, "International Journal of Project Management", 18, 51-59 [OpenAIRE]

Ardit D (1985) Construction Productivity Improvement, "Journal of Construction Engineering and Management", 111(1), 19528-19542

Arditi D. and Albulak Z. (1986), Line of Balance Scheduling in Pavement Construction, "Journal of Construction Engineering and Management", 112(3) [OpenAIRE]

Arditi D., Tokdemir O. B. and Suh K. (2001), Effect of learning on line-of-balance scheduling, "International Journal of Project Management", 19, 256-277

Assaf S. A and Al-Sadiq S. (2006) Causes of delay in large construction projects, "International Journal of Project Management", 24, 349-357

Atkinson R, (1999); Project Management: cost, time and quality, two best guesses and a phenomenon, it's [its] time to accept other success criteria; "International Journal of Project Management", 17(6), 337-342

Austin S.et al. (2002) Modelling and managing project complexity, "International Journal of Project Management", 20, 191-198

Ballard G. and Howell G (1998), Shielding Production: Essential Step in Production Control, "Journal of Construction Engineering and Management", 124(1) 11-17

Ballard, G and Howell, G (2003), Competing construction management paradigms; Proceedings of the A S C E Construction Research Congress, Hawaii, 19-23 March

Birrel, G. S (1980), Construction Planning - Beyond the Critical Path, "Journal of Construction Engineering and Management", 10, 389-407

Bryman A and Bell E. (2011) "Business Research Methods", 3rd ed, Oxford Uni. Press

Cheng-Leong A . et al. (1999) IDEF*: a comprehensive modelling methodology for the development of manufacturing enterprise systems; "Int. J. Prod. Res" 37(17), 3839- 3858

Chin K. S., et al. (2006) Integrated Integration Definition Language 0 (IDEF) and coloured Petri nets (CPN) modelling and simulation tool: a study on mould-making processes, "Int. Journal of Prod. Research", 44, (16), 3179 - 3205

38 references, page 1 of 3
Powered by OpenAIRE Research Graph
Any information missing or wrong?Report an Issue